How Do I Determine the Amount of the Claim of Lien?

The Claim of Lien must accurately state the contract amount and the amount actually unpaid and owing as of the date that the Claim of Lien is executed. It should not include monies for work not yet performed. Florida Statutes section 713.01(7) provides the rather complex definition of “contract price” and should be consulted when preparing a Claim of Lien. Essentially, the amount stated as being owed in the Claim of Lien should reflect:

  1. Properly authorized extras and change orders that either increase or decrease the contract amount; and
  2. Increases or decreases attributable to changes in the scope of work; and
  3. Increases or decreases attributable to defects in the work performed; and
  4. Decreases attributable to the contractor’s failure to fully perform the contract where the contractor has substantially performed the contract; and
  5. Increases or decreases attributable to other breaches of the contract; and
  6. Allowance items when accepted by the owner; and
  7. Liquidated damages provided for in the contract, except that no penalty or liquidated damages in the direct contract between the owner and the contractor affect the lien amount of any other lienor.

Contractors, i.e., lienors with a direct contract with the owner other than laborers, materialmen or professional lienors, must also substantially perform their direct contract in order to be entitled to a lien in the amount of the full contract price.

Pursuant to a 1999 amendment to the statutes, when materials have been specially fabricated for the project, but have not yet been incorporated into the project, the contract price, or in the absence of a set contract price, the reasonable value of the specially fabricated materials, must be separately stated in the Claim of Lien.

If there is no agreed upon price in the contract, then the lien amount should be the value of all labor, materials and/or services covered by the contract, subject to the seven (7) enumerated items, above.

The Claim of Lien should include interest on the amount owed if the contract provides for interest at a different rate than the current statutory prejudgment interest rate; however, it is a prudent practice to state the interest amount and the contract rate of interest separately in the Claim of Lien; for example, “$50,000.00, plus interest at the contract rate of eighteen percent (18%) per annum from 1/1/00.”

The lien amount should not include any attorney’s fees the lienor has incurred, or estimates it may incur, in enforcing the lien rights as attorney’s fees are not recoverable until a lawsuit has been commenced for the foreclosure of the lien.

The lien amount should not include, as separate items, the lienor’s overhead and profit; however, these items are recoverable if they are included in the total contract price. The value of unperformed future work, lost future profits on unperformed work, and cancellation, restocking, or similar charges for returned materials should not be included in the lien amount. Considerable caution should be exercised in regard to the inclusion in the lien amount of the value of labor, services, or materials which are the subject of pending change orders, as the inclusion of such amounts may be determined by a court to be a willful exaggeration of the lien amount, thereby, rendering the entire lien unenforceable and fraudulent and giving rise to certain remedies in favor of the owner discussed in more detail, below.

Go to Where to Record a Claim of Lien

Back to Establishing a Construction Lien

Back to Construction Liens

Back to Contractor Resources

DISCLAIMER AND CAUTION: THESE MATERIALS ARE PROVIDED FOR GENERAL INFORMATIONAL PURPOSES ONLY AND ARE NOT INTENDED NOR SHOULD THEY BE CONSTRUED AS LEGAL ADVICE AS TO ANY PARTICULAR SET OF FACTS OR CIRCUMSTANCES. DUE TO THE COMPLEXITY OF THE CONSTRUCTION LIEN LAW STATUTES AND THE CASES INTERPRETING AND APPLYING THE STATUTES, IT IS RECOMMENDED THAT COMPETENT LEGAL COUNSEL BE CONSULTED IN REGARD TO ANY QUESTIONS AS TO THE APPLICABILITY OF CONSTRUCTION LIEN LAW TO ANY SET OF PARTICULAR FACTS.

| Home | About Us | News and Articles | Construction Resources | Directions | Contact Us |

The hiring of an attorney is an important decision that should not be based solely upon advertising. Before you decide, ask us to send free written information about our qualification and experience.

DISCLAIMER: This website is intended to supply general information to the public. Although the information is generally accurate, it cannot be guaranteed. The nature of both Legislation and court decisions is that laws change quickly and visitors should always insure that legal information is accurate before relying on it. The information in this website applies to the laws in the State of Florida. The laws in other jurisdictions may be very different. This information is necessarily brief and may or may not apply to your situation, and should not be relied upon without additional consultation of an experienced attorney . In all cases, please consult an attorney before acting. This website is informational material only and is not intended to be solicitation or legal advice. Nothing on this website shall lead to the creation of an attorney-client relationship absent a written representation letter, signed by all parties, including Moody & Shea, P.A. The use of the internet, including e-mail, for the transmission of confidential or sensitive information is discouraged.

(c) Copyright, 2000-2006, Moody And Shea, P.A.